Alexco Production at Bellekeno Pending Water License
Submitted by Admin on Tue, 07/06/2010 - 18:54
The development of Alexco’s mine and mill at Bellekeno is on schedule for completion for commissioning and start-up of the mill in the third quarter of 2010. The issuance of the Type A Water Use License is the last major step after completion of the mill and mine to commence operation. The Type A Water License has been submitted in a form and substance adequate for the Yukon Water Board to render a decision.